Project Update: Oct. 17
Submitted Oct 17, 2011
During the week of October 7 through October 13, Herlihy worked on getting the bridge ready for concrete. All the supporting falsework is installed and all the reinforcing steel is on the deck. The embankment operations continued west of the Fox River. Additionally, some of the final landscape seeding started.
In the next week, the contractor will pour the bridge deck for the structure over the Fox River Trail. The earthwork operations will near their completion west of the river. The final landscaping east of the river will also continue.