Project Update: Oct. 24
Submitted Oct 31, 2011
During the week of October 14 through October 20, Herlihy poured the bridge deck for the Red Gate Road structure over the Fox River Trail. They have also excavated and formed the approach pavements east and west of the bridge. There was also some grading, topsoil, and landscaping work done by subcontractors.
In the next week, Herlihy will pour the approach pavements and start the final items of work on the bridge. The grading & topsoil work will continue as well.