Project Update: Oct. 31
Submitted Oct 31, 2011
During the week of October 21 through October 27, Herlihy poured the approach pavements and parapets for the bridge over the Fox River Trail. Herlihy continued removing their formwork and cleaning up the jobsite. Finally, there was some grading and spreading of topsoil west of the river.
In the next week, Herlihy will continue working on the final elements of the bridge. There will also be final grading, topsoil spreading, and landscaping work.