Project Update: Nov. 7
Submitted Nov 4, 2011
During the week of October 28 through November 3, Herlihy poured the east and west approach pavements as well as the parapet wall on top off the east approach pavement. The subcontractor continued the final grading. A separate subcontractor started the final landscape seeding.
In the next week, Herlihy will work to clean up the entire project site. Final embankment, grading and seeding operations will continue. Finally, the railing on the new bridge across the Fox River Trail will be installed.